The challenge:

A data centre concentrates server halls, UPS banks, chillers and cooling infrastructure onto a single footprint — and the white-space floor that sits on top of it has to stay level to millimetre tolerances for the life of the building. Rack alignment, containment, cabling and the mechanical plant above all depend on a foundation that does not move. That makes the piling package the single most load-critical and schedule-critical element on the site. The client required a professional piling foundation contractor who could deliver at speed and scale with professionalism.

 

On this project in Jaipur, UNO WORKS was engaged to deliver the complete pile foundation package: 750 bored cast-in-situ piles in 1000 mm and 1200 mm diameter. Three conditions defined the job:

 

1. A very large pile count on a single site. Seven hundred and fifty large-diameter piles is not a foundation; it is a production programme. Every activity — setting out, boring, cage fabrication, concreting, testing, spoil removal — had to run as a synchronised line rather than as discrete operations, or the numbers simply do not close inside a commercial programme.

 

2. A congested, live urban site. The plot is hemmed in by occupied buildings. During execution, neighbouring structures stood within metres of the working area, an adjacent reinforced concrete frame was under construction behind timber-and-bamboo formwork support, and members of the public were watching proceedings from the rooftop of an adjoining building. In that environment, vibration-free execution, controlled spoil management and hard barricading are not optional — and bored cast-in-situ piling, rather than driven piling, is the only defensible choice.

 

3. Dry, abrasive strata. The site ground is dry sandy-clayey silt, which produces heavy spoil volume and abrasive wear on tooling, and offers little natural bore stability in the upper layers. Casing discipline through the collar is what keeps the top of each 1200 mm bore true.


Our approach

UNO WORKS deployed SANY SR 155 Hydraulic Piling Rigs — a crawler-mounted rotary machine suited to large-diameter bores — supported by our own casings, Crane, Farrana for cage-handling and concreting resources.


UNO WORKS piling crew in PPE with SANY SR 155 hydraulic rotary rig at data centre pile foundation site, Jaipur
The UNO WORKS site team at the Jaipur data centre piling works, with SANY SR 155 hydraulic rotary rig on the working platform.

 

The methodology:

 

Grid setting out and guide casing. 

Each of the 750 pile positions was surveyed against the structural grid, with temporary steel casing installed to hold line and level at the collar. On a site of this density, a 50 mm setting-out error at grid level becomes a pile-cap clash later.

 

Boring and strata verification. 

Bores were advanced by rotary auger with the strata logged continuously, and founding level ratified against the geotechnical investigation before the bore was accepted. On 1200 mm piles the volume of concrete per metre is unforgiving — a wrong founding level is an expensive correction.


Reinforcement cages. 

Cages were fabricated ahead of demand to GFC drawings, with cover spacers fixed to secure the specified cover in the bore.


 

Concreting. 

Placed by tremmie under positive head, with continuous volume measurement against theoretical bore volume to detect over-break or necking as it happens, not after the fact.

 

Spoil and logistics management. 

With 750 large-diameter bores, spoil is a logistics problem in its own right. Removal was scheduled as a continuous cycle so that the working platform stayed trafficable for rigs, cranes and concrete vehicles.


 

Testing and records. 

Pile logs, pour records, cube results and integrity testing maintained pile-by-pile as a live quality record, so acceptance was progressive rather than a single end-of-project audit.

 

Execution on site

Running a 750-pile campaign means the site operates like a factory. Rigs were sequenced to the structural grid and moved only on prepared, load-bearing platforms; cage fabrication ran one step ahead of the rigs; concrete supply was matched to pour windows; and each pour was signed off before the rig relocated.


Safety management on this site centred on the risks that actually existed there: deep excavation and open bores, rig stability on a shared working platform, lifting operations for reinforcement cages, edge protection at the plot boundary, and public separation — barricades and controlled access to keep onlookers, including those on the adjacent rooftop, clear of the working radius.

 

The outcome

UNO WORKS completed approximately 750 bored cast-in-situ piles in 1000 mm and 1200 mm diameter for the Jaipur data centre, handing over a tested foundation to the follow-on structural package.

 

The significance is in the combination: large-diameter piling at genuine scale, executed without vibration in a live urban neighbourhood. That is the specific problem most data centre and industrial clients in Indian cities actually have — a constrained brownfield or infill plot, occupied neighbours, and a foundation that still has to be perfect.


Piling contractor for data centres across India

 

UNO WORKS is the execution arm of Ubuntu & Orenda, delivering bored cast-in-situ pile foundations from 600 mm to 1200 mm diameter for data centres, industrial facilities, institutional buildings, metro rail and bridge substructures across Rajasthan and India. We work with owned hydraulic piling rigs, in-house site engineering and a documented quality trail from pile log to integrity test — and we deliver On Time and In Full.

 

Planning a data centre foundation in Rajasthan or anywhere in India? Talk to our piling team at

+91-7019741174 or email at projects@uno-works.com about your pile layout, diameters and founding depths.

Recent Posts

See All
Slope Stabilization - Hills

Slope stabilization refers to any implemented technique that aims to stabilize an unstable or inadequately stable slope. The purpose of...

 
 
 

Comments


bottom of page